A_map_of_New_England,_being_the_first_that_ever_was_here_cut_..._places_(2675732378).jpg
RWhitcomb-editor RWhitcomb-editor

Tim Faulkner: The lessons of the long Cape Wind saga

Foundations_NREL.jpg

 

Via ecoRI News (ecori.org)

NARRAGANSETT, R.I. — Cape Wind may be gone, but it’s still fresh on the minds of attendees and speakers at a two-day southern New England wind energy conference hosted by the University of Rhode Island Graduate School of Oceanography.

Bill White, senior director of wind development for the Massachusetts state agency that advances renewable energy, said the demise of Cape Wind was a personal disappointment, but the 16-year saga offered several teachable moments for the offshore wind industry.

Those lessons, White said, include building further offshore, presumably away from popular recreation and fishing areas such as Nantucket Sound. To speed up permitting, environmental studies should be completed and regulations addressed earlier in the application process, he added.

Cape Wind also established offshore infrastructure that will benefit future projects. It led to construction hubs such as the New Bedford Marine Commerce Terminal, and laid the groundwork for planning, staging, and construction of turbines and their transmission lines.

“Cape Wind in a way served as a catalyst not just for Massachusetts but in a way for the entire East Coast in educating us to the possibility of offshore wind,” White said.

Smaller is better, Deepwater Wind CEO Jeffrey Grybowski said. He noted that the 130-turbine Cape Wind project and other failed offshore wind farms suffered from a process that was pushed by developers rather than by a state-driven model, such as the one Rhode Island embraced for the five-turbine Block Island Wind Farm.

Developers, inspired by large European wind projects, relied on analysis from engineers showing the maximum number of turbines that could be built in an offshore zone, Grybowski said. Large projects like Cape Wind and others off the coasts of Delaware, New Jersey and Long Island “were in essence drawn up on a white board in a developer’s office."

"They were engineered," Grybowski said. "An engineer said, ‘I can build this much in this area.’ They were mechanically engineered and financially engineered to those particular project sizes. And those projects failed.”

Grybowski praised Rhode Island’s ocean mapping plan for providing the locations and process for approving offshore wind projects. Through community and stakeholder involvement, the project was reduced from 100 turbines to eight and then five.

“When you are doing something for the first time going for the large size is not necessarily the right way to go, even though it may make financial sense,” Grybowski said.

Building 400 turbines is feasible and already happening in Europe, he said, “but starting small makes a lot of sense when you look at the long term.”

Starting small and moving slowly makes it easier to recover from mistakes that might derail a larger project. Grybowski didn’t mention specific errors, but the Block Island project encountered some safety and construction problems, along with minor public resistance, all of which were fixed or addressed with alternative plans.

Grybowski described the give-and-take as “enlightened self-interest.” He explained that the turbines benefited Block Island by fulfilling its dual goals of ending its reliance on diesel-fuel power, while connecting the island to the mainland power grid. As an inducement, the transmission line included a fiber-optic Internet connection.

“It means ... making the right concessions for the community and the project that maximizes everyone's goals at the end of the day,” Grybowski said.

The experience of building the Block Island Wind Farm set the course for new and much larger offshore wind projects that will be needed as the country transitions away from fossil fuels. Electrification of the transportation sector and advances in battery storage are escalating the demand for renewable energy and offshore wind is the most practical source of utility-scale power to meet that energy need, according to Grybowski.

Fake news


Science was the focus of the two-day conference (Dec. 11 and 12), with sessions on marine mammals, fish and fisheries, birds, and bats. Grybowski urged scientists to do more to promote their research. Climate-change deniers, Grybowski said, were given legitimacy because scientists didn't adequately “engage in that public conversation.”

“When there was pushback, fake news on the other side, the science community, they were comfortable with kind of putting their studies together," he said. “They weren’t really comfortable engaging in a real way out with people on the other side in the community. So I ask you to do that."

Grybowski pointed to news stories that circulated a dubious claim that noise from the Block Island Wind Farm killed a humpback whale that washed ashore on Jamestown earlier this year.

“When that sort of thing happens, it would be really great to have some researchers who were willing to step up and actually get engaged in that conversation and provide facts and help people make clear judgements about what is and what isn’t happening,” Grybowski said.

Tim Faulkner writes for ecoRI News.

Read More
RWhitcomb-editor RWhitcomb-editor

Bill Koch gets his way

 

From Robert Whitcomb's "Digital Diary,'' in GoLocal24.com:

Incredibly, the Cape Wind project, first proposed in 2001, has hung on since then, despite being held up by fierce opposition mostly funded and led by Bill Koch, one of the billionaire right-wing Koch Brothers, who have big fossil-fuel investments. Mr. Koch has a big summer place in Osterville, on the south shore of Cape Cod. He didn’t  want to look at  the wind turbines that Energy Management Inc., the Cape Wind developers, has wanted to put on an underwater sand bar  called Horseshoe Shoal in the middle of Nantucket Sound. On a clear day, the wind farm would be visible on the far horizon from Mr. Koch’s estate. But he’s rarely in Osterville. He has other houses. Still, like most members of the American plutocracy, he’s used to getting his way wherever he is.

Despite seemingly  endless obstacles, Energy Management Inc. has continued to make the $88,000 annual federal lease payments on the offshore tract and the Feds recently decided to let the enterprise maintain its long-term lease of the 46-square-mile area. But someone connected with EMI called me Friday to say that the company has decided to give up.  They’re worn out by the fight.

Too bad. The site, considering its geology, electric-grid proximity, nearby population density and in some other ways, might have been the best place for a big electricity-generating facility on the East Coast.

The lease would have been valid through 2041!

Read More
RWhitcomb-editor RWhitcomb-editor

Offshore windpower: They'll come to love it

Excerpted from the Sept. 1 "Digital Diary'' column in GoLocal24.

It’s too bad that it has taken so long, but the completion of Deepwater Wind’s five-turbine wind farm off Block Island, R.I., is very good news for New England.

The facility, expected to start producing electricity inNovember, will mean that a little more of New England’s electricity will come from the region’s own sources andthat we might be able to use a little less natural gas from fracking.  That process, contrary to the corporate publicity and wishful thinking, does not slow global warming because the process releases so much methane from the fracking sites.  And the Block Island project will help reduce air pollution:  The island’s electricity has been produced by unavoidably dirty diesel fuel.

Further, success in getting this project up will boost, by example, much bigger offshore windpower projects planned for  nearby waters,  most notably between the eastern tip of Long Island and Martha’s Vineyard. Eventually, this should dramatically improve the reliability of our electricity and in the long run cut its cost as windpower technology improves.

As usual with such projects in places like Block Island, Deepwater Wind had to fend off some affluent summer people who were offended that they’d have to look at wind turbines (which many folks think are beautiful) on their horizon.  Most famously, a group of very few rich people in Osterville, Mass., led by Bill Koch (of the Koch Brothers) have managed to block the big Cape Wind project, which was to go up in middle of Nantucket Sound,  although the project has been supported by a large majority of theMassachusetts public. Yet again,  a few privileged NIMBYs have sabotaged the public interest. (I co-wrote (with Wendy Williams) a bookabout that controversy, called Cape Wind, later made into a movie called Cape Spin.)

The Obama administration and some states, including Rhode Island and Massachusetts have, to their credit, enacted laws and regulations to encourage offshore wind. This is especially attractive in the Northeast, with its reliable breezes and shallow water extending a lot further offshore than you see off the West Coast.

The Europeans have long embraced offshore windpower, for environmental reasons and to reduce reliance on fossil-fuel imports, especially from an increasingly aggressive Russia.

I predict that many current offshore-windpower foes will come to tolerate and even like the turbines’  curious beauty. And the fishermen will  come to love them because fish congregate in the supports of such structures.

--  Robert Whitcomb

Read More
Commentary Robert Whitcomb Commentary Robert Whitcomb

B.I. wind farm and Lucky Sperm Club on Nantucket Sound

Why is construction starting on a wind farm off Block Island, R.I., while, despite 14 years of effort by Cape Wind developer Jim Gordon, nothing has gone up in Nantucket Sound?  And that's even with the Block Island project, Deepwater Wind, about three miles offshore while Cape Wind would be more than five miles offshore -- thus usually out of  sight from land in this hazy and windy region. Well, yes, the Block Island project is much smaller.

But the main  answer is  that Block Island project doesn't have as rich and ruthless a billionaire opponent as Bill Koch, from whose summer house in Osterville (which he only uses a very few weeks a year) you could see Cape Wind's turbines on a crystal-clear day. Mr. Koch, another member of the Lucky Sperm Club (his father founded the industrial empire from which Bill  Koch hugely benefits), has been willing to spend tens of millions of dollars to stop Cape Wind because he doesn't ever want to look at it.

He can take great pride in single-handedly stopping a project that would have provided about three-quarters of southeastern Massachusetts's electricity.

--- Robert Whitcomb

Read More
Commentary Robert Whitcomb Commentary Robert Whitcomb

Wind wins on Block Island

With surprisingly little fanfare, except in the glorious Block Island Times,  what   would be  the first offshore wind farm in America has received its final major  regulatory approval, from the Army Corps of Engineers. It's on schedule to be  up and running in two years. The Block Island Wind Farm --  Deepwater Wind's five-turbine , 30-megawatt operation  --  would lower Block Island's sky-high electricity costs and  would act as an encouragement for  backers of other, much bigger projects, such as the Cape Wind project, in Nantucket Sound. That project has been held up for years by Osterville, Mass., summer resident and fossil-fuel mogul Bill Koch.

How difficult it has become to do big projects in America, especially when a few local rich people don't like them!

 

 

Read More
Uncategorized Robert Whitcomb Uncategorized Robert Whitcomb

Philip K. Howard: Infrastructure repairs drown in regulatory molasses

  To our readers: This column also ran in a pre-renovation version of  New England Diary a few weeks ago. As we seek to import the pre-renovation archives, we will rerun particularly important files, such as  Philip Howard's piece here.

-- Robert Whitcomb

By PHILIP K. HOWARD

 

NEW YORK

President Obama went on the stump this summer to promote his "Fix It First" initiative, calling for public appropriations to shore up America's fraying infrastructure. But funding is not the challenge. The main reason crumbling roads, decrepit bridges, antiquated power lines, leaky water mains and muddy harbors don't get fixed is interminable regulatory review.

Infrastructure approvals can take upward of a decade or longer, according to the Regional Plan Association. The environmental review statement for dredging the Savannah River took 14 years to complete. Even projects with little or no environmental impact can take years.

Raising the roadway of the Bayonne Bridge at the mouth of the Port of Newark, for example, requires no new foundations or right of way, and would not require approvals at all except that it spans navigable water. Raising the roadway would allow a new generation of efficient large ships into the port. But the project is now approaching its fifth year of legal process, bogged down in environmental litigation.

Mr. Obama also pitched infrastructure improvements in 2009 while he was promoting his $830 billion stimulus. The bill passed but nothing much happened because, as the administration learned, there is almost no such thing as a "shovel-ready project." So the stimulus money was largely diverted to shoring up state budgets.

Building new infrastructure would enhance U.S. global competitiveness, improve our environmental footprint and, according to McKinsey studies, generate almost two million jobs. But it is impossible to modernize America's physical infrastructure until we modernize our legal infrastructure. Regulatory review is supposed to serve a free society, not paralyze it.

Other developed countries have found a way. Canada requires full environmental review, with state and local input, but it has recently put a maximum of two years on major projects. Germany allocates decision-making authority to a particular state or federal agency: Getting approval for a large electrical platform in the North Sea, built this year, took 20 months; approval for the City Tunnel in Leipzig, scheduled to open next year, took 18 months. Neither country waits for years for a final decision to emerge out of endless red tape.

In America, by contrast, official responsibility is a kind of free-for-all among multiple federal, state and local agencies, with courts called upon to sort it out after everyone else has dropped of exhaustion. The effect is not just delay, but decisions skewed toward the squeaky wheels instead of the common good. This is not how democracy is supposed to work.

America is missing the key element of regulatory finality: No one is in charge of deciding when there has been enough review. Avoiding endless process requires changing the regulatory structure in two ways:

Environmental review today is done by a "lead agency"—such as the Coast Guard in the case of the Bayonne Bridge—that is usually a proponent of a project, and therefore not to be trusted to draw the line. Because it is under legal scrutiny and pressure to prove it took a "hard look," the lead agency's approach has mutated into a process of no pebble left unturned, followed by lawsuits that flyspeck documents that are often thousands of pages long.

What's needed is an independent agency to decide how much environmental review is sufficient. An alteration project like the Bayonne Bridge should probably have an environmental review of a few dozen pages and not, as in that case, more than 5,000 pages. If there were an independent agency with the power to say when enough is enough, then there would be a deliberate decision, not a multiyear ooze of irrelevant facts. Its decision on the scope of review can still be legally challenged as not complying with the basic principles of environmental law. But the challenge should come after, say, one year of review, not 10.

It is also important to change the Balkanized approvals process for other regulations and licenses. These approvals are now spread among federal, state and local agencies like a parody of bureaucracy, with little coordination and frequent duplication of environmental and other requirements. The Cape Wind project off the coast of Massachusetts, now in its 12th year of scrutiny, required review by 17 different agencies. The Gateway West power line, to carry electricity from Wyoming wind farms to the Pacific Northwest, requires the approval of each county in Idaho that the line will traverse. The approval process, begun in 2007, is expected to be complete by 2015. This is paralysis by federalism.

The solution is to create what other countries call "one-stop approvals."  Giving one agency the authority to cut through the knot of multiple agencies (including those at state and local levels) will dramatically accelerate approvals.

This is how "greener" countries in Europe make decisions. In Germany, local projects are decided by a local agency (even if there's a national element), and national projects by a national agency (even though there are local concerns). One-stop approval is already in place in the U.S. New interstate gas pipelines are under the exclusive jurisdiction of the Federal Energy Regulatory Commission.

Special interests—especially groups that like the power of being able to stop anything—will foster fears of officials abusing the public trust. Giving people responsibility does not require trust, however. I don't trust anyone. But I can live with a system of democratic responsibility and judicial oversight. What our country can't live with is spinning our wheels in perpetual review. America needs to get moving again.

Philip K. Howard, a lawyer, is chairman of the nonpartisan reform group Common Good. His new book, "The Rule of Nobody," will be published in April by W.W. Norton. He is also the author of, among other works, "The Death of Common Sense''.

Read More