Foot by foot

New England Clean Energy Connect map

 Adapted from Robert Whitcomb’s “Digital Diary,’’ in GoLocal24.com

There’s recently been progress, albeit still too slow, on making New England’s energy greener. 

First, there’s that a  state jury in Maine  has voted 9-0 to let proceed the long-delayed transmission line for moving electricity from Hydro Quebec into our region. In a deeply dubious move, foes of the line, including three companies with natural-gas facilities in the state, had sought to kill the Avangrid Inc. project, called New England Clean Energy Connect. They did this by putting up a ballot question approved by voters after a massive campaign against the project that was aimed at retroactively killing Avangrid’s  project, which regulators had approved. Armed with permits, the company had already spent hundreds of millions of dollars  before the ballot question to clear the wooded, mostly wilderness route, logically assuming that it could legally do so. Talk about unfair

The jury verdict came in the wake of a Maine Supreme Judicial Court ruling that in effect backed the continuation of the project.

It seems that as of this writing that the project will be completed, adding more   clean juice to the region’s grid to such other new green-energy production as also-too-long-delayed offshore wind projects and solar. (Will nuclear fusion to generate electricity  eventually be our savior? Research on it, much of it happening in New England, is coming along at a good clip.)

Utility Dive reported:

Anne George, spokesperson for ISO New England (which manages the region’s grid), said that it’s pleased that the project can move forward.

“The New England states’ ambitious climate goals will require building significant amounts of new infrastructure in a region where building infrastructure has been difficult,’’ she said.

Phelps Turner, a senior lawyer at the Conservation Law Foundation, said the delay caused by the legal challenge is “symptomatic of building energy infrastructure in New England.”

“We lost a lot of time.’’

New England, despite many of its citizens’ progressive rhetoric, is a remarkably Nimby place, in energy matters, housing and some other fields. Many Red States have done far more than New England in setting up  renewable-energy operations.

Hit this link.

Then there are such  little noted options as geothermal. Consider National Grid’s pilot program at the University of Massachusetts at Lowell. The company will use boreholes to see if a geothermal  network can be established there using piping and pumps to pull heat out of the ground to warm the university’s buildings in cold weather and then pump heat from them into the ground to cool them in the summer.

Hit this link.

#New England Clean Energy Connect

Read More
RWhitcomb-editor RWhitcomb-editor

Tim Faulkner: More hurdles for plans to import Quebec electricity

Proposed New England Clean Energy Connect project.

Proposed New England Clean Energy Connect project.

Via ecoRI News (ecori.org)

News continues to get worse for the Northern Pass project and efforts to deliver Canadian hydropower to southern New England.

On May 24, the New Hampshire Site Evaluation Committee denied an appeal by Northern Pass to overturn the decision that rejected the 192-mile-long high-voltage transmission line though the state.

The siting committee initially rejected the $1.6 billion project on Feb. 1 because of concern that the network of unsightly power lines and towers would harm tourism, local businesses and the environment.

According to the siting board, the appeal failed because there was no new information to review. And despite objections by Northern Pass, the positive elements of the application had been considered in the initial decision, committee members said.

"If there were conditions they could meet to approve it, we would have approved it with those conditions," said Bill Oldenburg of the Site Evaluation Committee in a video of the meeting taken by WMUR-TV, of Manchester, N.H.

In an online statement, Northern Pass, a joint venture between Eversource and Hydro-Québec, said it remains committed to the project and is considering taking the siting committee’s decision to court.

“We intend to pursue all options for making this critical clean energy project a reality, along with the many economic and environmental benefits for New Hampshire and the region. This opportunity to significantly lower energy costs for customers should be given great weight,” said Eversource New Hampshire president Bill Quinlan. “Large infrastructure projects of this scale often face challenges during the siting process, and we will continue to work with all of the stakeholders to present a project that receives New Hampshire’s approval.”

Meanwhile, Massachusetts, which has agreed to a 20-year power-purchase agreement for Northern Pass energy, has shifted its focus from Northern Pass to New England Clean Energy Connect (NECEC), a power-line transmission project that delivers Québec hydropower through western Maine to Lewiston, Maine, and on to Massachusetts.

The 145-mile project has broad community support, including from Maine Gov. Paul LePage.

The transmission system is opposed by the environmental group  (NRCM), which says the project will damage 53 miles of forest. The conservation group worries that NECEC won’t receive the same vetting as Northern Pass.

“Rather than allowing Maine regulators to go through the same thoughtful process that led New Hampshire to reject that project, Gov. Paul LePage, through a spokesperson, has vowed to ram the project through Maine’s Department of Environmental Protection,” according to a March 19 NRCM statement.

The Boston Globe editorial board criticized opponents of NECEC for overlooking the 1,200 megawatts of low-emission-creating electricity and the tax revenue it will bring to communities along the route.

The financial benefits are far less than the $200 million in tourism funding and $30 million in annual tax revenue promised by Northern Pass. So far, local taxes are the only revenue promised by NECEC.

State and local lawmakers are now rethinking their initial support for the project, in hopes of increasing the financial benefits to the state. There is also concern over the fact that none of the hydropower will be available for in-state use. Local renewable-energy projects will also be unable to connect to the power lines.

NECEC is being developed by Hydro-Québec and the utility Central Maine Power, a subsidiary of the multinational corporation Avangrid.

The Massachusetts Department of Energy Resources and state utilities are negotiating a power-purchase contract with Central Maine Power for the project. The agreement must be approved by the Massachusetts Department of Public Utilities. State permits are expected by the end of 2018. Federal permits are expected in 2019.

Tim Faulkner is a journalist with ecoRI News.

Read More
RWhitcomb-editor RWhitcomb-editor

Tim Faulkner: Northern Pass decision delayed again

-- Pro-Northern Pass map

-- Pro-Northern Pass map

Via ecoRI News (ecori.org)

The Northern Pass hydropower transmission-line project isn't dead yet, but time is running short for the $1.6 billion project.

On March 12, the New Hampshire Site Evaluation Committee (SEC) voted, 5-0, to defer a request to reopen the deliberation process. The committee did agree to suspend its Feb. 1 oral vote to deny the project but only until the written decision is released later this month. A decision on whether to restart hearings won’t be made until May.

The March 12 meeting was held at the request of Northern Pass in an effort to somehow convince the SEC to rehear and reverse its Feb. 1 decision to reject the project. Soon after that vote, Massachusetts, the primary buyer of the electricity, gave the developer, Eversource Energy, until March 27 to salvage the proposal.

“This is just really a Hail Mary effort on Northern Pass’s part,” said Melissa Birchard, staff attorney for the Conservation Law Foundation. “It was a long shot and they knew it. But they just wanted to make an effort to satisfy the Massachusetts’ ultimatum.”

Opponents say the project threatens 95,000 acres of forestland and could harm scenic tourist areas. Small towns fear the project would hurt business and disrupt their communities.

New Hampshire Gov. Chris Sununu endorsed the 192-mille high-voltage system for the jobs and the promise of lower electric bills for ratepayers. He was disappointed that the siting board rejectedthe project on Feb. 1.

Massachusetts agreed to buy a portion of the 1.09 gigawatts of so-called "low-carbon energy" to meet its Clean Energy and Climate Plan for 2020.

In the meantime, the Bay State selected a backup plan, the New England Clean Energy Connect, developed by the Central Maine Power Co., to bring Canadian hydropower to Massachusetts. 

There has been no response from the Massachusetts Department of Energy Resources regarding the recent SEC decision to postpone any action on the Northern Pass until May.

On Feb. 28, Eversource Energy filed a request to vacate the SEC's decision saying it wanted to elaborate on efforts to address the objections to the project. According to Eversource, the impacts on tourism and property values would be offset through payments from a $200 million state fund. Also, Eversource says alternative construction methods would be used lessen impacts on businesses.

Eversource claims the project will create 2,600 jobs during constriction, save New Hampshire ratepayers $62 million annually, add $30 million to state and local tax revenue annually, and reduce regional carbon emissions by more than 3 million tons a year.

The project received good news March 6 when the Canadian National Energy Board approved the proposal, thereby completing the last of the permits for the construction between Eversource Energy and Hydo-Quebec, a Canadian government-run utility.

Eversource issued the following statement after the March 12 decision by the SEC:

“We hope it is an indication that the SEC will evaluate the required statutory criteria, as well as thoroughly consider all of the conditions that could provide the basis for granting approval. At a time when the region needs new and diverse sources of clean energy, it is vitally important that projects like Northern Pass are considered fully and efficiently and without unnecessary delay.”

Tim Faulkner is a reporter and writer for ecoRI News.

Read More
RWhitcomb-editor RWhitcomb-editor

Tim Faulkner: Mass. may get electricity from Hydro-Quebec another way

The spillway at Hydro-Quebec's  Robert-Bourassa generating station can deal with a water flow twice as large as the Saint Lawrence River.

The spillway at Hydro-Quebec's  Robert-Bourassa generating station can deal with a water flow twice as large as the Saint Lawrence River.

Via ecoRI News (ecori.org)

The Northern Pass power-line project may be on life support, but controversial Canadian hydropower might yet reach southern New England if Massachusetts Gov. Charlie Baker gets his way.

The New Hampshire Site Evaluation Committee rejected the 192-mil-long Northern Pass project on Feb. 1. While Eversource Energy has until March 27 to salvage its $1.6 billion transmission plan, Massachusetts has announced negotiations with a Maine utility for a backup plan to deliver imported hydropower to the Bay State.

The New England Clean Energy Connect, developed by the Central Maine Power Co., proposes a 145-mile power-line network to transmit 1,200 megawatts of hydropower from the Canadian border to Lewiston, Maine, where it will connect to the New England power grid. The $950 million cost for the project would be spilt by ratepayers and Hydro-Québec, an energy company run by the Canadian government.

Baker is banking on Canadian hydropower to fulfill his goal of 1,200 megawatts of new renewable energy under contract by April 1. The terms of the deal, as set by state law, have been criticized for excessively benefiting the utility, which in this case is Eversource or Central Maine Power. The terms for a hydropower-transmission project allows the utility to collect an annual payment, as well as receive a fully funded, high-voltage transmission system.

New Hampshire Republican Gov. Chris Sununu supports the Northern Pass proposal, but there was overwhelming opposition from local politicians, environmentalists and the public. In a unanimous vote, the state siting board ultimately rejected the proposal 7-0 because of concern that it would damage scenic areas, tourism and local businesses.

In Massachusetts, the bidding process has been accused of favoring the utilities, who make up a majority of the selection committee. Massachusetts Attorney General Maura Healey is reviewing the bidding process for any violations.

Less publicized is the threat hydropower inflicts on the environment and indigenous communities in Québec. Hydro dams require massive reservoirs that swamp dry land and low-lying wetlands while distressing fish and their habitat.

Indigenous groups such as the Pessamit Innu, Cree and Inuit claim that hydropower causes permanent damage to their land, food supply and the salmon population, one of the primary sources of revenue in the Betsiamites River. The Pessamit Innu tribe says exporting additional Hydro-Quebec electricity would cause greater changes in the water level of the reservoirs and further damage the environment.

The New Hampshire energy siting board denied the Pessamit Innu a request to intervene in the Northern Pass application review. The Pessamit grievances date back to the 1950s, when the first dams were built on their tribal land without approval, by Hydro-Quebec, which runs 62 hydro projects in the region. The company maintains that it has worked with the indigenous groups to protect and restore the salmon population while paying the Pessamit $80 million over 20 years. Hydro-Quebec notes that the company has signed 30 agreements with indigenous groups, known as first nations, since 1975.

Hydro-Quebec chasticed the Pessamit for partnering with Sierra Club to advance its opposition to exporting hydropower. The power company also criticized the environmental group for arguing that hydropower doesn't reduce greenhouse-gas emissions.

Yet, according to the Union of Concerned Scientists, large-scale hydropower contributes to global warming, as flooded land releases carbon dioxide and methane from decaying vegetation and erosion caused by runoff.

A 2016 study by Washington State University suggests that methane and CO2 emissions released as the water level fluctuates in hydropower reservoirs should be considered in the lifecycle emissions of an energy facility. A 2016 study published by PLOS One reaches a similar conclusion, but suggests that the emissions can be offset by generating biogas electricity and timely management of power generation.

Tim Faulkner is a reporter and writer for ecoRI News, where this article first appeared.

 

 