Tim Faulkner: N.H. panel's rejection of Northern Pass hydro-energy project upends Mass. plans
Via ecoRI News (ecori.org)
By all accounts, the rejection of the Northern Pass energy project was a major surprise. The plan to deliver 1.09 gigawatts of hydropower from Quebec through New Hampshire to southern New England via high-voltage transmission lines was all but assured by the developer and energy officials in Massachusetts. The Massachusetts Department of Energy Resources was counting on the electricity for its Clean Energy and Climate Plan for 2020.
A Massachusetts Clean Energy power-purchase contract was recently awarded to Eversource and Hydro-Quebec for hydro electricity to help meet the state's goal of 1,200 megawatt of new land-based power by 2022. Eversource intended to start construction in April and complete the project by 2020.
On Feb. 1, however, the New Hampshire Site Evaluation Committee rejected the proposal, 7-0. The board worried that the 192-mile power-line system, including hulking towers, would disrupt main streets and harm tourism, particularly in the scenic northern portion of the state that is home to the White Mountain National Forest and Franconia Notch.
Eversource made concessions by promising to bury 52 miles of the route and set aside 5,000 acres of preservation and recreation land. But it wasn't enough. The decision was celebrated by small towns and environmental groups that vigorously opposed the project since it was announced in 2010. Thousands of New Hampshire residents submitted comments objecting to the project.
Eversource said it was “shocked and outraged” by the vote and plans to appeal the decision in New Hampshire Supreme Court. It has 30 days to appeal the vote by the site evaluation committee.
“The process failed to comply with New Hampshire law and did not reflect the substantial evidence on the record,” Eversource said in a prepared statement.
The utility referred to the economic benefits of the $1.6 billion project, including $30 million in annual tax revenue, as well as the renewable-energy goals it would be fulfilling. The process, Eversource said, “is broken and this decision sends a chilling message to any energy project contemplating development in the Granite State.”
Eversource had invested some $250 million in the project and received approval from the U.S. Department of Energy for a portion of the power lines last November, but still requires a permit from Quebec.
In Massachusetts, the office of the attorney general and the Executive Office of Energy and Environmental Affairs (EEA) said they would reevaluate the energy procurement decision, while remaining committed to acquiring imported hydropower.
Peter Lorenz, EEA communications director, said a new proposal for renewable energy would be considered if existing contracts can't meet the terms of the agreement.
Rhode Island has also shown interest in imported hydropower. Former Gov. Lincoln Chafee advocated for a deal with Hydro-Quebec after touring the company. In recent years the state discussed buying a portion of Quebec hydropower in a deal with Massachusetts but an agreement was never reached.
On Feb. 5, Gov. Gina Raimondo announced a goal of acquiring 400 megawatts of utility-scale renewable energy from the Northeast, but only small-scale hydro projects qualify for the program.
Tim Faulkner writes for ecoRI News.
Jane A. Difley/John D. Judge: Time to bury the huge Northern Pass power project
It’s time for the out-of-state and out-of-country interests pushing the current Northern Pass proposal to bury the private transmission line along appropriately designated transportation corridors. A similar project in Vermont shows that it can be done.
The fast-track toward approval of the 154-mile New England Clean Power Link, which recently received a Presidential Permit from the U.S. Department of Energy, highlights the benefits of burying transmission lines along state highways. That project has leapfrogged Northern Pass in the quest for permitting by using 56 miles of existing road rights-of-way and running along the floor of Lake Champlain. It would serve the same purpose as Northern Pass by enabling Canadian hydropower generators to market more energy to southern New England.
In terms of scenic degradation, vulnerability to catastrophic weather events and alteration of prized public lands, Northern Pass has it all wrong. Perhaps that’s why, six years since its proposal went public, the opposition to Northern Pass among New Hampshire residents is stronger than ever.
New Hampshire’s citizens know that Northern Pass as proposed is a wrong-headed project and that its more than 1,000 steel towers across 192 miles would destroy the state’s lifeblood: the iconic scenic views that draw millions of visitors to the state’s mountains and forests, feeding our tourism-dependent economy. Furthermore, Northern Pass is wholly incompatible with such conservation gems as the White Mountain National Forest and the Appalachian National Scenic Trail, both of which would be hurt.
New Hampshire’s people know that it is wrong to have our scenic beauty and environmental legacy sacrificed for the money-making interests of private power producers.
At public meetings and hearings, and in written testimony, the public has spoken out against this damaging and unnecessary project. Thirty-one towns that would be affected have voted to oppose it.
The U.S. Department of Energy has received more than 7,500 comments, largely negative, about Northern Pass. Given that public push-back, the DOE is studying no fewer than 24 alternatives to the project.
By comparison, things on the Vermont side of the border look very different. The Clean Power Link project has generated just 12 written comments. Two alternatives were reviewed in its Draft Environmental Impact Statement, which was released in May, just one year after the application was submitted.
The environmental impact of the Vermont project appears to be far less than the impact of the Northern Pass proposal. Using modern technology, the Vermont cables would rest in a 4-foot-deep-by-4-foot-wide trench alongside public rights of way, or submerged in Lake Champlain. TDI, the transmission developer, will pay the State of Vermont $21 million annually for its use of road rights-of-way and will create an additional $298 million Public Good Benefit Fund.
In contrast, what would New Hampshire get? Steel towers 155-feet high looming over the tree canopy and scarring scenic views. Negative impacts on resources of regional and national significance. The danger of power outages due to wind, snow and ice storms due to vulnerable, overhead lines. Damage to the state’s tourism economy, and no lease payments to support the state budget.
The Appalachian Mountain Club, the Society for the Protection of New Hampshire Forests and our respective members have long defended New Hampshire’s scenic landscapes. As we contemplate the Northern Pass vision, we are reminded of another wrong-headed proposal.
In the 1950s, the Feds proposed blasting a four-lane superhighway through Franconia Notch. We objected. Ultimately, a compromise was reached and the two-lane Franconia Notch Parkway was built.
The Northern Pass proposal is mired in a contentious state permitting process with a very uncertain outcome. We believe that it’s time that the executives at Eversource and Hydro-Quebec recognize that their own interests may be best served by respecting the wishes of New Hampshire people and the landscapes we cherish. We call on Eversource and Hydro-Quebec to look at the benefits of the Vermont model and put forward a proposal that buries Northern Pass for its entire length.
There are many who point to the downsides of importing more power from Quebec and call for no new transmission lines. We see no need for the Northern Pass project. But burying the Northern Pass would prevent at least the selling out of New Hampshire and the natural resources of regional and national significance on which the livelihoods of Granite State citizens depend.
For more information on the status of unprecedented fight against the Northern Pass proposal, visit https://www.forestsociety.org/advocacy-issue/northern-pass or http://www.outdoors.org/conservation/hot-issues/northern-pass.cfm
Jane Difley is president/forester for the Society for the Protection of New Hampshire Forests. John D. Judge is president of the Appalachian Mountain Club.
PCFR dinner on Hydro-Quebec, Trudeau, etc.
Feb. 2, 2016
To members and friends of the Providence Committee on Foreign Relations (thepcfr.org; pcfremail@gmail.com). (We update the Web site frequently with news and commentary. Information on how to join the PCFR is on the site, too.)
Speaking to us next, at our Tuesday, Feb. 16, dinner meeting, will be David Alward, the former premier of New Brunswick and now the consul general of Canada to New England.
He’ll talk about the implications of the recent change in Ottawa under new (rock star?) Prime Minister Justin Trudeau, international security issues, such big trade matters as New England’s purchase of more hydro-electric power from Canada, the U.S.-Canada border and the idea of a common market encompassing Canada, the U.S. and Europe.